HOME > Business Area> BIO GAS RESOURCES INDUSTRY |
|
|
| |
 |
 |
|
| Location |
Seoul Sewage Treatment Center (Phase I) |
| Scale |
Upgrading Bio Gas Product & Supply : 4,200§©/day |
| Project Type |
Foreign Investment
B.O.T.(Build Operate Transfer) |
| Operating Period |
- Design/Construction : 2008.1 ~ 2008.12
- Operation : 2009.1 ~ 2023.12 (15 year) |
| Participants |
Operation Authority : Seoul Metropolitan Government
Management : Eco energy holdings Co., Ltd |
| Capacity |
7,000§©/day |
| Objective |
Promotion example project of bio gas vehicle fuel in Seoul
Establishment of the renewable energy project
Acquisition carbon credit and upgrading the sewage treatment center
Supply Low-Emission Vehicle |
|
|
| |
 |
 |
|
| Plant Capacity |
50MW Electric Power Plant by Steam Turbine / Generator
(LFG Consumption Rate : About 550N§©/min) |
| Location |
58 Baekseok-Dong, Seo-Gu, Incheon
Sudokwon Landfill Site
Waste Water Treatment Facilities |
| Investment |
By Private Enterprises |
| Owner |
Eco Energy Co.,Ltd.
(The Consortium of Eco Energy Holdings And KIAMCO) |
| Project Type |
B.T.O.(Build Transfer Operate) |
| Operating Period |
For 11 years (2003~2017) |
|
|
| |
 |
 |
|
| Purpose |
Extracting and supplying fuel gas for district heating source |
| LFG Consumption Rate |
About 165N§©/min) |
| Location |
481-36 Sangam Dong, Mapo-gu, Seoul |
| Owner |
Korea Urban Home Heating Corporation |
| Project Type |
B.T.O.(Build Transfer Operate) |
| Period of maintaining Management |
For 6 years (2002~) |
|
|
| |
 |
 |
|
| Plant Capacity |
3MW Electric Power Plant by LFG Engine
(LFG Consumption Rate : About 33N§©/min) |
| Location |
San 21, Kumgo-Dong, Yoosung-Gu, Daejeon |
| Investment |
By Private Enterprises
(Hyosung corporation, Eco Energy Holdings
) |
| Owner |
Daejeon Metropolitan City |
| Project Type |
B.T.O.(Build Transfer Operate) |
| Operating Period |
For 10 years (2003~) |
|
|
| |
 |
 |
|
| Plant Capacity |
1.5MW Electric Power Plant + 130 m3/min Medium BTU
(LFG Consumption Rate : About 130N§©/min) |
| Location |
421 Bang cheon-Ri, Dasa-Eup, Dalsung-Gun, Daegu |
| Investment |
By Private Enterprises
(Hyosung corporation, Eco Energy Holdings ) |
| Owner |
Daegu Metropolitan City |
| Project Type |
B.T.O.(Build Transfer Operate) |
| Operating Period |
For 20 years (2006~) |
|
|
| |
|
| |